C&H Commercial Contractors v. United States
Facts
Plaintiff held a fixed-price Army Corps contract to reconstruct a runway and later sought damages for three alleged government-caused delays: late issuance of the notice to proceed, temporary unavailability of the work site due to design oversights, and delay from additional asphalt testing. The contract incorporated the Suspension of Work clause and inspection clauses requiring the contractor to maintain quality control and permitting additional testing of nonconforming work at the contractor's expense. Plaintiff produced no detailed schedules or other proof showing how the alleged delays affected overall performance, and two modifications addressed the work-site and asphalt matters, each containing release language for costs and delays related to the change.
Issue
Did plaintiff prove entitlement to delay damages under the Suspension of Work clause for the three alleged periods of delay, and was the asphalt-testing claim barred by accord and satisfaction under a contract modification?
Rule
To recover under the Suspension of Work clause, a contractor must show that performance was delayed, the government directly caused the delay, the delay was unreasonable, and the delay caused injury in the form of increased cost or loss. A critical path analysis is not invariably required, but the contractor must present specific evidence that the government's delay affected performance or increased costs; bare allegations are insufficient. A bilateral modification with release language bars later claims when the evidence shows a mutual settlement of the disputed matter, including impacts and delay costs.
See the holding & full analysis
Create a free KwikCourt account to unlock the rest of this brief — and practice the case.
- The court's holding and reasoning
- Doctrine tests, pitfalls & exam hypotheticals
- 10 practice questions + 4 AI-graded essays on this case
Test yourself
If Maple Crest seeks delay damages under a Suspension of Work clause, what is the strongest argument against recovery?