Jacob & Youngs, Inc. v. Kent
Facts
The plaintiff built the defendant's country residence and sought to recover an unpaid balance after construction was completed and the defendant occupied the house. The contract specifications required wrought iron pipe of Reading manufacture, but some pipe installed was made by other manufacturers. The omitted brand resulted from the subcontractor's oversight, not fraud or willfulness, and the difference was not noticed even by the defendant's architect during inspection. Replacing all the non-Reading pipe would have required demolition of substantial parts of the completed structure because the plumbing was largely enclosed within the walls.
Issue
When a builder has substantially performed a construction contract but innocently deviates from a specification in a trivial way, may the owner withhold final payment on the theory that literal compliance was a condition of recovery? If not, is the proper measure of damages the cost of replacement or the difference in value?
Rule
A contractual promise in a construction contract is not automatically treated as a condition of the builder's right to recover when the departure from the contract is trivial and unintentional. If the defect is unsubstantial and the cost of completion or replacement is grossly and unfairly out of proportion to the good to be attained, the owner's allowance is measured by the difference in value rather than the cost of replacement; willful transgressors are not entitled to such mitigation.
See the holding & full analysis
Create a free KwikCourt account to unlock the rest of this brief — and practice the case.
- The court's holding and reasoning
- Doctrine tests, pitfalls & exam hypotheticals
- 10 practice questions + 4 AI-graded essays on this case
Test yourself
If Harbor Crest Builders sues for the unpaid contract balance, which is the strongest argument that Lena may not refuse payment entirely?