Kenford Co. v. County of Erie
Facts
In 1969, Erie County contracted with Kenford and Dome Stadium, Inc. for construction and operation of a domed stadium near Buffalo. The agreement required the County to begin construction within 12 months and provided that if the parties could not agree on a 40-year lease, an appended 20-year management contract for DSI would be executed once the stadium was completed and available for use. The parties never agreed on a lease, and the County never began construction, resulting in a breach. DSI sought damages for the profits it claimed it would have earned operating the stadium for 20 years.
Issue
May a plaintiff recover lost prospective profits for a contemplated 20-year operation of a stadium where the facility was never built and the proof of profits rested on expert economic projections? More specifically, were such profits within the parties' contemplation and capable of proof with reasonable certainty?
Rule
Loss of future profits for breach of contract may be recovered only when the plaintiff shows with certainty that the damages were caused by the breach, that the alleged loss is capable of proof with reasonable certainty rather than speculation, and that the particular damages were fairly within the contemplation of the parties when the contract was made. When the claimant is a new business, a stricter standard applies because there is no established track record from which profits can be estimated with the required certainty.
See the holding & full analysis
Create a free KwikCourt account to unlock the rest of this brief — and practice the case.
- The court's holding and reasoning
- Doctrine tests, pitfalls & exam hypotheticals
- 10 practice questions + 4 AI-graded essays on this case
Test yourself
Under the governing rule, what is the strongest reason a court should deny Lakefront’s claim for lost future profits?