Lujan v. G & G Fire Sprinklers, Inc.

Supreme Court of the United States · 2001 · Administrative Law
Administrative LawDue ProcessProcedural Due ProcessPublic ContractsFourteenth Amendmentprocedural due processproperty interestbreach of contract

Facts

California's Labor Code required prevailing wages on public works projects and authorized awarding bodies to withhold payments due a contractor when a subcontractor failed to comply with the Code. If money was withheld from the contractor because of a subcontractor's violations, the contractor could withhold sufficient sums from the subcontractor. In 1995, the California Division of Labor Standards Enforcement determined that G & G had failed to pay prevailing wages and failed to keep or furnish payroll records, then directed awarding bodies on three projects to withhold sums equal to wages and penalties. The contractors withheld corresponding amounts from G & G, and G & G claimed the total withheld exceeded $135,000.

Issue

Whether California's statutory scheme for withholding payments on public works projects violates the Fourteenth Amendment's Due Process Clause when a subcontractor receives no predeprivation or postdeprivation hearing before or after the withholding. More specifically, the question was whether due process required a prompt hearing when the subcontractor's asserted interest was a contractual claim for payment.

Rule

Where the asserted property interest is a claim for payment under a contract, and state law makes ordinary judicial process available to resolve that contractual dispute, that process satisfies procedural due process. Due process is not a fixed set of procedures applicable in every situation; its requirements depend on the nature of the interest at stake.

🔒

See the holding & full analysis

Create a free KwikCourt account to unlock the rest of this brief — and practice the case.

  • The court's holding and reasoning
  • Doctrine tests, pitfalls & exam hypotheticals
  • 10 practice questions + 4 AI-graded essays on this case
Sign up free to see more →
Free sample · practice this case

Test yourself

One of 10 multiple-choice questions for this case. Pick an answer to see why.
The City of Denver hires Summit River Builders as prime contractor for a public library project, and Summit hires Elena Cruz Drywall as a subcontractor. After a state labor office concludes Elena failed to comply with wage terms incorporated into the public contract, the city withholds funds from Summit, and Summit withholds the same amount from Elena; Colorado law allows Summit or its assignee to sue the city on the contract for the withheld sum, but no administrative hearing is provided.

Elena brings a § 1983 procedural due process claim, arguing that the lack of any predeprivation or postdeprivation hearing automatically violates the Fourteenth Amendment. What is the strongest response?

Explanation. The majority held that, assuming state action and a protected property interest, due process was satisfied where the claimant's asserted interest was a claim for payment under a contract and state law provided ordinary judicial process to resolve that dispute. The Court rejected the idea that a hearing is invariably required in this setting. (Derived from Lujan v. G & G Fire Sprinklers, Inc. (2001).)