Merritt-Chapman & Scott Corp. v. United States
Facts
Plaintiff's predecessor contracted with the Army Corps of Engineers to construct locks and dam works, but an existing state highway crossed part of the work site and had to be relocated before plaintiff could excavate the middle lock wall area. The contract stated the old highway would be opened to plaintiff about December 1, 1955, but the Government did not make it available until April 14, 1956, and did not issue a formal suspension order, so plaintiff kept men and equipment mobilized. Plaintiff claimed increased excavation costs, idled equipment costs, and overall delay costs from the Government's failure to turn over the site on time. The Board later denied recovery on the ground that plaintiff lacked an underpass during part of the period and that abnormal rainfall would have delayed it anyway.
Issue
Under the pre-1960 Suspension of Work Clause, was plaintiff entitled to an equitable adjustment when the Government's failure to turn over part of the site caused an unreasonably long constructive partial suspension, even though the Board found other factors such as the absence of an underpass and heavy rainfall would also have delayed performance? A further issue was whether this court or the Board should determine quantum.
Rule
Under the pre-1960 Suspension of Work Clause, once a Government-caused suspension unreasonably delays the work, the entitlement question is whether that delay caused any additional expense or loss to the contractor. The contractor may recover if the Government's delay was the proximate cause of additional loss, even if some other occurrence might hypothetically have caused a like delay during the same period; recovery is denied only if the Government's delay did not cause the additional loss because some other superseding intervening factor caused the loss independently. A constructive suspension has the same effect and consequences as an actual suspension, and damages must be assessed as if the suspension order should have been issued.
See the holding & full analysis
Create a free KwikCourt account to unlock the rest of this brief — and practice the case.
- The court's holding and reasoning
- Doctrine tests, pitfalls & exam hypotheticals
- 10 practice questions + 4 AI-graded essays on this case
Test yourself
Under a pre-1960 Suspension of Work Clause, which is the strongest basis for Pine Harbor's entitlement to relief?