HomeCase briefs › Civil Procedure

Natural Resources Defense Council, Inc. v. U.S. Nuclear Regulatory Commission

United States Court of Appeals for the District of Columbia Circuit · Civil Procedure
Civil ProcedureAdministrative LawNEPAAtomic Energy ActAPANEPAhard lookEIS

Facts

The NRC issued Strata Energy a license to conduct in situ leach uranium mining at the Ross Project in Wyoming, and the Councils intervened in the licensing proceeding. Their admitted contentions challenged, among other things, analysis of groundwater restoration to alternate concentration limits, adequacy of hydrological information regarding excursions, and cumulative impacts related to broader Lance District development. The Board declined to migrate one cumulative-impacts contention to the draft EIS, refused a new contention concerning the entire Lance District, and later found one FEIS deficiency regarding information on post-mining aquifer restoration to ACLs at other sites. The Board concluded that staff hearing testimony supplemented the FEIS, rejected the remaining contentions, and the Commission affirmed before the Councils sought judicial review.

Issue

Whether the NRC acted arbitrarily, capriciously, or contrary to NEPA when it refused to migrate or admit certain contentions, allowed the FEIS deficiency to be cured through post-licensure supplementation in the hearing record, and rejected the Councils' substantive objections concerning aquifer restoration and off-site groundwater contamination risks. More specifically, the court had to decide whether any identified procedural imperfection required remand and whether the Commission's technical judgments lacked adequate support.

Rule

Under APA review, a court asks whether the agency took the requisite NEPA 'hard look' at environmental consequences and will not invalidate agency action for minor deficiencies or flyspeck the analysis. An agency adjudicator need not scour the record to supply arguments or good-cause showings a party failed to present. A project is not a 'connected' action requiring joint EIS treatment if it has independent utility and does not depend on future related projects for justification. Although NEPA contemplates that environmental information be available before decisionmaking, remand is unnecessary when the agency publicly cures the identified deficiency before judicial review, the licensing decision remains amendable or rescindable, and remand would be futile because the agency has already considered the missing information.

🔒

See the holding & full analysis

Create a free KwikCourt account to unlock the rest of this brief — and practice the case.

  • The court's holding and reasoning
  • Doctrine tests, pitfalls & exam hypotheticals
  • 10 practice questions + 4 AI-graded essays on this case
Sign up free to see more →
Free sample · practice this case

Test yourself

One of 10 multiple-choice questions for this case. Pick an answer to see why.
Blue Mesa Minerals applied for a federal materials license for a recovery project near Casper, Wyoming. An intervenor had filed a contention attacking the application’s two-paragraph cumulative-impacts discussion, but when the agency later issued a draft EIS, that document contained a far more detailed and differently structured cumulative-impacts analysis; the intervenor moved only to "migrate" the old contention and never requested amendment or addressed any good-cause standard.

If the intervenor petitions for review after the board refuses migration, what is the strongest argument for upholding the board?

Explanation. The majority held that migration is appropriate only when the analysis challenged in the application and in the draft EIS is sufficiently similar. Where the later discussion materially differs, the adjudicator may refuse migration, and it need not scour the record to invent an amendment request or good-cause showing the party did not present. (Derived from Natural Resources Defense Council, Inc. v. U.S. Nuclear Regulatory Commission (n.d.).)