City of Rye v. Public Service Mutual Insurance Co.
Facts
Developers built six luxury cooperative apartment buildings under a plan approved by the City Planning Commission and intended to build six more. To obtain certificates of occupancy for the first six buildings, they agreed with the city to post a $100,000 bond and to pay $200 per day after April 1, 1971 for each day the remaining six buildings were not completed, up to the bond amount. More than 500 days passed without completion, and the city sought to recover the entire $100,000. No statute authorized the city to exact a penalty or forfeiture from the developers.
Issue
Whether the city's $100,000 bond arrangement and $200-per-day charge for delay in completing the remaining buildings constituted enforceable liquidated damages or an unenforceable penalty. More specifically, the question was whether, absent statutory authority, the bond reflected a reasonable estimate of probable monetary harm to the city.
Rule
Absent statutory authority authorizing a penal bond or forfeiture, general contract principles govern. A provision fixing damages in advance is enforceable as liquidated damages only when actual damages from breach are difficult to ascertain and the amount fixed is a reasonable measure of the anticipated probable monetary harm; if the amount is grossly disproportionate to anticipated harm, or if there is no anticipatable cognizable harm, the provision is an unenforceable penalty.
See the holding & full analysis
Create a free KwikCourt account to unlock the rest of this brief — and practice the case.
- The court's holding and reasoning
- Doctrine tests, pitfalls & exam hypotheticals
- 10 practice questions + 4 AI-graded essays on this case
Test yourself
If Nora challenges the forfeiture as an unenforceable penalty, which is the strongest response?