Muldoon v. Lynch
Facts
Plaintiffs contracted to complete improvements on defendant's cemetery lot, including a marble monument, for a total price of $18,788, with $11,887 due upon completion. The contract required completion of most work within four months and the monument within twelve months, 'under forfeiture of ten dollars per day for each and every day beyond the stated time for completion.' The monument was delayed for nearly two years because the large marble blocks procured in Italy had to await a direct ship to San Francisco, but once they arrived the work was completed according to contract and the only dispute was over the delay. Plaintiffs claimed the full unpaid balance, while defendant argued that $7,820 should be deducted as liquidated damages for the delay.
Issue
Whether the contract clause imposing a 'forfeiture of ten dollars per day' for delay in completion should be enforced as liquidated damages or treated as a penalty, so that defendant could not deduct it without proof of actual damage.
Rule
Parties may agree in advance on damages for breach when, from the nature of the case, it would be impracticable or extremely difficult to fix actual damage. But if the contract shows that the stated sum was intended as a forfeiture or penalty rather than as compensation, courts will treat it as a penalty, and the party claiming it must prove actual damages; language of 'forfeiture' strongly imports a penalty, and a sum materially disproportionate to any reasonable estimate of actual loss will not be treated as liquidated damages.
See the holding & full analysis
Create a free KwikCourt account to unlock the rest of this brief — and practice the case.
- The court's holding and reasoning
- Doctrine tests, pitfalls & exam hypotheticals
- 10 practice questions + 4 AI-graded essays on this case
Test yourself
If Cascade Lantern Builders sues for the unpaid balance, how should a court most likely treat the $400-per-day clause?