Southwest Engineering Company v. United States
Facts
Southwest entered into four federal construction contracts, each with a completion date and a per diem liquidated damages clause for delay. The contracts also provided that the contractor would not be charged for delays due to unforeseeable causes beyond its control, including acts of the Government, and administrative proceedings granted time extensions for excusable delays. After those extensions and one partial remission, the Government withheld $8,300 for delay beyond the administratively extended completion dates. The parties stipulated that although the projects were completed late, the Government suffered no actual damage on any project.
Issue
May the Government enforce contractual liquidated damages for delay after administratively crediting excusable or government-caused delays, even though the Government caused some delay and ultimately suffered no actual damages? Does the stipulation of no actual damage make the delay clause an unenforceable penalty?
Rule
Federal law governs federal contracts. A liquidated damages clause is enforceable, rather than a penalty, when at the time of contracting the stipulated amount is a reasonable forecast of just compensation for anticipated harm and the harm is incapable or very difficult of accurate estimation. The clause is judged as of the time the contract was made, not by later events, and proof that actual damages were less than, or even nonexistent, does not bar recovery. Government-caused delay does not defeat liquidated damages for other days of delay attributable to the contractor, so long as the contractor is relieved for the excusable or government-caused days.
See the holding & full analysis
Create a free KwikCourt account to unlock the rest of this brief — and practice the case.
- The court's holding and reasoning
- Doctrine tests, pitfalls & exam hypotheticals
- 10 practice questions + 4 AI-graded essays on this case
Test yourself
If Riverton argues the clause is unenforceable solely because the agency admits it suffered no actual damage, how should a court rule?